B64 SHEET PILING (WEST) PARTIALLY COMPLETE
CX PUMPS CASING DRIVING IN PROGRESS
CX PUMP CASING WELDING IN PROGRESS
PILECAP B1 PEDESTAL CONCRETING
APPLICATION OF DAMP PROOFING COATING ON ZONE B PILECAPS
STARY OF PILECAP C10 ZONE C
INSPECTION OF ZONE A PEDESTALS
INSPECTION OF ZONE A PEDESTALS