11 May, 2015

11.05.15

GENERAL VIEW OF BOILER WORKS FROM THE EAST 

 INSTALLING PILE REBAR CAGE IN ZONE B

 CASTING PILE IN BOILER ZONE B

 CASTING BOILER PILE IN ZONE A

 BORING PILE IN BOILER ZONE A

ADDITIONAL TRIAL MIXES IN SITE BATCHING PLANT UNIT 1

09.05.15

BOILER PILE REBAR CAGE PREFABRICATION

 
BORING BOILER ZONE A PILES

 BORING BOILER ZONE A PILES 

 REBAR CAGE INSTALLATION ZONE A

CASTING BOILER ZONE A 1200MM DIA PILE 

 BORING BOILER ZONE B

 GENERAL VIEW FROM EAST LOOKING WEST OVER THE BOILER WORKS


08.05.15

 BORING BOILER ZONE B PILES

 BORING BOILER ZONE C PILES

 CASTING BOILER ZONE B PILE

PILING RIG RELOCATING IN BOILER ZONE B

 PILING RIG ZONE B

DELIVERING PREFABRICATED PILE REBAR CAGES 

CASTING ZONE B PILES 

 GENERAL VIEW OF BOILER PILING (EAST)


07 May, 2015

07.05.15

BAUER PILING COMMENCE PILING IN BOILER ZONE A
"21.05M LONG PILES" EAST (MILLS &  EAST SIDE OF FURNACE)

 PILING BALANCE OF WFGD ANCILLARY TANK FOUNDATIONS

INSTALLING CAGE ON BOILER ZONE A (P247)

BORING BOILER ZONE A PILES (P349)

 CASTING WFGD UNIT L39 PILES

CASTING LAST WFGD UNIT L39 PILE (L39-3)

TRIAL MIX RUNS ON SITE BATCHING PLANT UNIT 2 
(UNIT 1 OPERATIONAL & SUPPLYING SITE)

05 May, 2015

05.05.15

 PREFABRICATION OF B01 BOILER "LONG" 21.05M PILES 

 WFGD TANK PILES

STRIKING OF MLT RIG OFF B63 STH TP-B17 TO PREPARE FOR LATERAL TEST 

BAUER PILE REBAR CAGE PREFABRICATION  

SITE BATCHING PLANT UNIT 2 READY FOR TRIAL MIX 

SITE BATCHING PLANT UNIT 1 IS  OPERATIONAL
 - FIRST CONCRETE DELIVERED 2ND MAY 2015 

SITE BATCHING PLANT UNIT 1 IS  OPERATIONAL
 - FIRST CONCRETE DELIVERED 2ND MAY 2015  

NO WORKS BY CLIENT B/FILL CONTRACTOR DUE TO PUBLIC HOLIDAY

04.05.15

GENERAL SITE VIEW OF PILING OPERATION

BORED PILING ON LAST OF BOILER ZONE C 14.05M "SHORT" PILES

LIGNITE STRATA FOUND ON BOILER ZONE C PILES

CASTING PILES

INSTALLATION OF REBAR CAGES ON WFGD Lxx ANCILLARY TANK FOUNDATIONS

INSTALLATION OF SONIC LOGGER TUBES ON BOILER ZONE C SHORT PILE P164

LATERAL TEST ON B63 STH TP-B14

HEAVY RAIN AND WINDS FROM 1600HRS







30 April, 2015

30.04.15

 PILING COMMENCES ON WFGD L39 TANK FOUNDATION

SECOND BAUER BG25 RIG SET UP WITH DOUBLE CASING 
TOOL TO DRIVE 1200MM & 800MM WITH QUICK HITCH FOR CHANGING AUGERS 


BG24 RIG BORING BOILER ZONE C PILES 

BORING BOILER ZONE C PILES 

 DRY BORING BOILER ZONE C PILES 
                                                    
DELIVERY OF SITE PREFABRICATED REBAR CAGES FOR BOILER PILES 

APS SITE OFFICE FOOTINGS FOR GROUND BEAMS COMPLETED 
GROUND BEAM REBAR STARTED