11 May, 2015
07 May, 2015
07.05.15
BAUER PILING COMMENCE PILING IN BOILER ZONE A
"21.05M LONG PILES" EAST (MILLS & EAST SIDE OF FURNACE)
PILING BALANCE OF WFGD ANCILLARY TANK FOUNDATIONS
INSTALLING CAGE ON BOILER ZONE A (P247)
BORING BOILER ZONE A PILES (P349)
CASTING WFGD UNIT L39 PILES
CASTING LAST WFGD UNIT L39 PILE (L39-3)
TRIAL MIX RUNS ON SITE BATCHING PLANT UNIT 2
(UNIT 1 OPERATIONAL & SUPPLYING SITE)
05 May, 2015
05.05.15
PREFABRICATION OF B01 BOILER "LONG" 21.05M PILES
WFGD TANK PILES
STRIKING OF MLT RIG OFF B63 STH TP-B17 TO PREPARE FOR LATERAL TEST
BAUER PILE REBAR CAGE PREFABRICATION
SITE BATCHING PLANT UNIT 2 READY FOR TRIAL MIX
SITE BATCHING PLANT UNIT 1 IS OPERATIONAL
- FIRST CONCRETE DELIVERED 2ND MAY 2015
SITE BATCHING PLANT UNIT 1 IS OPERATIONAL
- FIRST CONCRETE DELIVERED 2ND MAY 2015
NO WORKS BY CLIENT B/FILL CONTRACTOR DUE TO PUBLIC HOLIDAY
04.05.15
GENERAL SITE VIEW OF PILING OPERATION
BORED PILING ON LAST OF BOILER ZONE C 14.05M "SHORT" PILES
LIGNITE STRATA FOUND ON BOILER ZONE C PILES
CASTING PILES
INSTALLATION OF REBAR CAGES ON WFGD Lxx ANCILLARY TANK FOUNDATIONS
INSTALLATION OF SONIC LOGGER TUBES ON BOILER ZONE C SHORT PILE P164
LATERAL TEST ON B63 STH TP-B14
HEAVY RAIN AND WINDS FROM 1600HRS
30 April, 2015
30.04.15
PILING COMMENCES ON WFGD L39 TANK FOUNDATION
SECOND BAUER BG25 RIG SET UP WITH DOUBLE CASING
TOOL TO DRIVE 1200MM & 800MM WITH QUICK HITCH FOR CHANGING AUGERS
BG24 RIG BORING BOILER ZONE C PILES
BORING BOILER ZONE C PILES
DRY BORING BOILER ZONE C PILES
DELIVERY OF SITE PREFABRICATED REBAR CAGES FOR BOILER PILES
APS SITE OFFICE FOOTINGS FOR GROUND BEAMS COMPLETED
GROUND BEAM REBAR STARTED