25 February, 2016

25.02.16

 Boiler View from West
 Boiler - 600 T main body arrived on site
 Boiler - 600 T South of Mills for boom erection
 Boiler overall view from East
 Boiler view from East / Back end
 Boiler Air Preheater area
 Boiler Air Preheater area
 Boiler 400 T crane working on air preheater steel
 Boiler PA/FD Fan North
 Boiler PA/FD Fan South
 Turbien Hall - View from South
 Turbine Hall - West pedestals
 Turbine Hall - Management EHS walkdown in center of Turbine Hall
 Turbine Hall - CW Intake - Sheet piles removed on 24th 
 Turbine Hall CW Intake
 Turbine Hall - CW Intake backfilling on North
 Turbine Hall - CW Intake from CEB excvation
 CEB excavation & Pile cutting
 Chimney stack - slip form on going
  Chimney stack - slip form on going
Cooling Tower - 4th part raft poured on 24th Feb (1,842 m3 in 12 hours finished @ 2 am on 25th) 

24.02.16


 Boiler steel - view from South to bunker bay
 Boiler steel - view from South to Back end
 Boiler steel - view from South East to Back end
Boiler steel - 400 T crane on air preheater steel
 Boiler general View from North East

 Boiler Mills preparation for sole plates installation
 Boiler Mills preparation for sole plates installation
Boiler Mills preparation for sole plates installation
 Boiler PA/FD Fans fondations South
 Boiler PA/FD Fans fondations North 
Turbine Hall - View from South
Turbine Hall - pedestals & CW intake from Boiler Mills
Turbine Hall - pedestals & CW intake from Transformers
Turbine Hall - From North East - CW Outfall & TH pedestals
 Turbine Hall - North Side- CW Intake backfilling
 Cooling Water pipes cofferdam to Cooling Towers
Cooling Water pipes cofferdam to Turbine Hall
 CEB excavation & pile cutting - UG networks
 CEB excavation & pile cutting - UG networks
 UG Nteworks 
 Chimney / Stack slip form on going
Chimney / Stack slip form on going

23 February, 2016

23.02.16

 Boiler steel erection (400T crane) - View from South East
 Boiler steel erection (tower crane & 250 T crane) - View Form North East
 Boiler Air preheater area / ESP duct fondation & UG ductbanks
Stack slip form progressing (10cm/hour up to 25 m heigth cold joint stop) 
 Stack slip form - Inside view 
 Cooling Water Pipes erection continues


22 February, 2016

22.02.16 (publicholiday)


Turbine Hall View West side
 Turbine Hall View East side
 Cooling Water pipes backfilling North of Turbine Hall
 Cooling water Pipes Intake to Turbine Hall
 CEB excavation and Pile cutting for CEB handover
 Boiler steel erection, Mills Bay, Tier #2
  Boiler steel erection, Mills Bay, Tier #2
  Boiler steel erection, Eats side & air preheater area
 Boiler Mill#A, packer plates installation for sole plates
 Boiler PA Fan progress, North side
 Boiler PA Fan progress, South side
 Boiler FD Fan, south side
 Cooling Tower, raft rebar progress
 Stack, slipform, started on 20th Feb @ 13h45 (1,4 m/ 12 m shift)
 Boiler material delivery: First mills
  Boiler material delivery: First mills
 Boiler material delivery: Mills part