25 February, 2016

25.02.16

 Boiler View from West
 Boiler - 600 T main body arrived on site
 Boiler - 600 T South of Mills for boom erection
 Boiler overall view from East
 Boiler view from East / Back end
 Boiler Air Preheater area
 Boiler Air Preheater area
 Boiler 400 T crane working on air preheater steel
 Boiler PA/FD Fan North
 Boiler PA/FD Fan South
 Turbien Hall - View from South
 Turbine Hall - West pedestals
 Turbine Hall - Management EHS walkdown in center of Turbine Hall
 Turbine Hall - CW Intake - Sheet piles removed on 24th 
 Turbine Hall CW Intake
 Turbine Hall - CW Intake backfilling on North
 Turbine Hall - CW Intake from CEB excvation
 CEB excavation & Pile cutting
 Chimney stack - slip form on going
  Chimney stack - slip form on going
Cooling Tower - 4th part raft poured on 24th Feb (1,842 m3 in 12 hours finished @ 2 am on 25th) 