26 February, 2016

26.02.16


  Boiler View from South West
 Boiler Multiple Piece sequence lift
Boiler steel - view from South to Back end


 B63 STH View from South West
  B63 STH View from South east
 B63 TH View from North
 B63 TH - CW Intake backfilled on North
B63 TH - CW Intake backfilled on North
 B63 Turbine Hall CW Intake
 Boiler - 600 T South of Mills erection
 B01 - Boiler PA/FD Fan Area South  
 B01 - Boiler PA/FD Fan Area North 
 B01/B17 Interface
 B01 Foundation detail
 B01 Area Duct Bank

 E12 - Circulating Water Pump Station Base rebar progress
 Cooling Water pipes cofferdam to Turbine Hall
 Cooling Water pipes cofferdam to Turbine Hall
 Cooling Water pipes cofferdam to Turbine Hall
  Chimney stack - slip form on going
  Chimney stack - slip form on going
 B30 CEB Excavation from North to South
Duct bank to CEB 
 Boiler Coal Silo Cone section prefabrication
Boiler Air Duct prefabrication