Turbine Hall (West) - CW pipes & saddles + pile caps & pedestals
Turbine Hall (East) - CW pipes & saddles + pile caps & Condensate Pumps shafts
Turbine Hall Table (B64) pile croping (1.5 m dia piles)
Boiler steel erection -mills bay - Tier # 2 progress
Boiler steel overview from North East (air preheater)
Boiler steel overview from East(air preheater)
Boiler steel in air preheater area from South East
Boiler Mills Bay
Boiler mills preparation for sole plates installation
Boiler columns grouting in Mills Bay
Boiler columns, ready for erection
Boiler column erection in air Preater area (400T + 70T tail)
Boiler bracing erection
Boiler East civil Interface: Air preheater/flue gas ducts
Boiler FD Fan North - backfilling started
Boiler PA fan North to start
Boiler PA Fan South
Boiler electrical Pit
Boiler Coal Silo prefabrication: Cone section & support girder at the back
Boiler Coal Silo Prefabrication: Barrel sections
CW Pipe detail (additonnal wrapping for concrete encasement)
CW Pipe erection progress from Turbine Hall, along Boiler North side
CW Pipe civil progress to West
CW Pipe civil progress to East
Piling for Air Preheater Wash Bassin (B94)
Excavation for underground water tanks
Cooling Water raft fondation continues
FGD Absorber reactor Tower foundation
Stack slip form preparation almost complete