15 February, 2016

15.02.16

 Turbine Hall (West) - CW pipes & saddles + pile caps & pedestals
 Turbine Hall (East) - CW pipes & saddles + pile caps & Condensate Pumps shafts
Turbine Hall Table (B64) pile croping (1.5 m dia piles) 
Boiler steel erection -mills bay - Tier # 2 progress 
Boiler steel overview from North East (air preheater)
Boiler steel overview from East(air preheater)
Boiler steel in air preheater area from South East
 Boiler Mills Bay
 Boiler mills preparation for sole plates installation
 Boiler columns grouting in Mills Bay
 
 Boiler columns, ready for erection
 Boiler column erection (400T + 70T tailing cranes)
 Boiler column erection in air Preater area (400T + 70T tail)
 Boiler bracing erection 
  Boiler East civil Interface: Air preheater/flue gas ducts
Boiler FD Fan North - backfilling started
Boiler PA fan North to start
Boiler PA Fan South
Boiler electrical Pit
 Boiler Coal Silo prefabrication: Cone section & support girder at the back
 Boiler Coal Silo Prefabrication: Barrel sections
 CW Pipe detail (additonnal wrapping for concrete encasement)
 CW Pipe erection progress from Turbine Hall, along Boiler North side
 CW Pipe civil progress to West
CW Pipe civil progress to East 
 Piling for Air Preheater Wash Bassin (B94)
 Excavation for underground water tanks
Cooling Water raft fondation continues
 
 FGD Absorber reactor Tower foundation 
 Stack slip form preparation almost complete