Boiler View to North from laydown area
Boiler backpass main girders
Boiler Furnace Main Girders preparation for strand jack installation
Boiler - Hot Primary Air Duct erection progress View to South
Boiler - Hot Primary Air Duct erection progress View to North
Boiler Pressure part ground fabrication area
Pressure Part ground fabrication - backpass wall panel buckstay installation
Air preheater View to North
Ductworks ground fabrication area
B95 Polishing Plant excavation
B63 STH South Pile Caps in progress
B30 CEB Blinding in progress