28 February, 2015

27.02.15

 SITE SITUATION TODAY

 AXIAL TENSILE LOAD TEST ON PILE TP02 ONGOING

 SETTING OF DIAL GAUGES

 PREPARATION OF TP09 FOR STATIC COMPRESSIVE LOAD TEST

 PREPARATION OF TP18 FOR STATIC COMPRESSIVE LOAD TEST

REINFORCEMENT PLACING FOR TP06

 PILING WORK FOR MC’S TEST PILES AT SOUTH-EAST ONGOING

 STEEL CAGE FABRICATION FOR MC'S TEST PILES 

 SITE PERIMETER FENCING AT SOUTH SIDE IN PROGRESS

CONTINUOUS STEEL REBAR DELIVERY  

27 February, 2015

26.02.15

 SITE SITUATION TODAY

 AXIAL TENSILE LOAD TEST ON TP02

 DYNAMIC LOAD TESTING (PDA) ON PILE TP011

 DYNAMIC LOAD TESTING (PDA) ON PILE TP018

 GAUGES ATTACHMENT ON THE PILE

 PILE DRIVING ANALYZER - TP018

 PILING WORK FOR MC’S TEST PILES ONGOING

 CABLE INSTALLATION FOR POWER SUPPLY TO TEMPORARY SITE FACILITIES

 FENCING AT SOUTH SIDE IN PROGRESS

LAND RECLAMATION BY EGAT

25 February, 2015

25.02.15

 STS  HOLDING A BRIEFING IN EGAT OFFICES BEFORE TO START WITH TESTING
 
 AXIAL TENSILE LOAD TEST ON TP02

 DIAL GAUGES FOR PILE SETTLEMENT MEASUREMENT

 PILE DYNAMIC TEST (PDA) ON PILE TP15

 NWRT’S MOBILE CRANE 120 T CAPACITY IS OPERATIONAL

 PREPARATION OF PILE CAPS IN PROGRESS

  MC'S PILES- REINFORCEMENT PLACING 

 MC'S TEST PILES- BORING

  FENCING WORK AT SOUTH SIDE IN PROGRESS

WORKS FOR POWER SUPPLY TO TEMPORARY SITE FACILITIES ONGOING

24 February, 2015

24.02.15

   SAFETY INDUCTION EVERY TUESDAY MORNING, FOR REMINDING ZERO TOLERANCE POLICY & SAFETY FIRST.
 STS IS READY FOR AXIAL TENSILE LOAD TEST ON TP02 

LOADS FOR MAINTAIN LOAD TEST ON TP01 READY

 DEMOLISHING OF PILE HEADS IN PROGRESS

 PREPARATION OF REINFORCEMENT FOR PILE CAPS ON GOING

 STRIKING OF  FORMWORK 

 CURING OF PILE CAPS REGULARLY 

 SURVEYOR TEAM AT EAST SIDE FOR SETTING OUT OF MC’S TEST PILES

 PILING WORK FOR MC’S TEST PILES AT SOUTH-EAST IN PROGRESS

NWRT’S MOBILE CRANE 120 TON CAPACITY IS ALMOST OPERATIONAL

23 February, 2015

23.02.15



 STS PREPARING FOR AXIAL TENSILE LOAD TEST ON TP02

 LAST REACTION PILES 20/1 CONCRETED ON 21/02/2015

 PILE HEAD DEMOLISHING AND REINFORCEMENT PLACING FOR OTHER PILE CAPS ONGOING

  CONCRETING OF PILE CAPS IN PROGRESS

  CURING OF ALREADY POURED PILE CAPS ONGOING

HYDRAULIC JACKS FOR TESTING

 
ARRIVAL OF NWRT’S MOBILE CRANE 120 T CAPACITY 

 FENCING OF WEST, NORTH AND EAST SIDE COMPLETED AND AT SOUTH SIDE IN PROGRESS

 POLES INSTALLATION FOR POWER SUPPLY TO TEMPORARY SITE FACILITIES ALMOST COMPLETED

CONTINUOUS DELIVERY OF STEEL REBAR