20 February, 2015

20.02.15

Fig 1. SITE VIEW TODAY

Fig 2. BORING OF REACTION PILE 21/2

Fig 3. BORING OF REACTION PILE 20/2 

Fig 4.  REINFORCEMENT PLACING FOR REACTION PILE 19/1
Fig 5.  PLACING OF STEEL CAGE FOR REACTION PILE 8/1

Fig 6. CONCRETING OF REACTION PILE 20/2

Fig 7. CONCRETING OF REACTION PILE 8.1

Fig 8. REINFORCEMENT PLACING FOR PILE CAP B01

 Fig 9. CONTINUOUS DELIVERY OF STEEL REBAR

Fig 10.  POLES INSTALLATION FOR POWER SUPPLY TO TEMPORARY SITE FACILITIES