28 February, 2015

27.02.15

 SITE SITUATION TODAY

 AXIAL TENSILE LOAD TEST ON PILE TP02 ONGOING

 SETTING OF DIAL GAUGES

 PREPARATION OF TP09 FOR STATIC COMPRESSIVE LOAD TEST

 PREPARATION OF TP18 FOR STATIC COMPRESSIVE LOAD TEST

REINFORCEMENT PLACING FOR TP06

 PILING WORK FOR MC’S TEST PILES AT SOUTH-EAST ONGOING

 STEEL CAGE FABRICATION FOR MC'S TEST PILES 

 SITE PERIMETER FENCING AT SOUTH SIDE IN PROGRESS

CONTINUOUS STEEL REBAR DELIVERY  