18 February, 2015

18.02.15



 Fig 1. EARLY START IN THE MORNING

 Fig 2. BORING OF PT08 - 800 DIA

 Fig 3. START BORING RP 6/1, WHILE RP 5/1 COMPLETED 

 Fig 4. RP 5/1 - REINFORCEMENT PLACING 

 Fig 5. CONCRETING OF RP 6/1 

 Fig 6. EXCAVATION WORK FOR Nos. 9 PILE CAPS COMPLETED 

 Fig 7. DEMOLISHING AND REMOVAL OF PILE HEAD TP01

 Fig 8. REBAR STORAGE, NEAR TO TP01, WILL BE USED AS KENTLEDGE  

 Fig 9. REBAR PROCUREMENT ONGOING

           Fig 10.  AREA READY FOR INSTALLATION OF TEMPORARY OFFICES  