STS PREPARING FOR AXIAL TENSILE LOAD TEST ON TP02
LAST REACTION PILES 20/1 CONCRETED ON 21/02/2015
PILE HEAD DEMOLISHING AND REINFORCEMENT PLACING FOR OTHER PILE CAPS ONGOING
CONCRETING OF PILE CAPS IN PROGRESS
CURING OF ALREADY POURED PILE CAPS ONGOING
HYDRAULIC JACKS FOR TESTING
ARRIVAL
OF NWRT’S MOBILE CRANE 120 T CAPACITY
FENCING OF WEST, NORTH AND
EAST SIDE COMPLETED AND AT SOUTH SIDE IN PROGRESS
POLES
INSTALLATION FOR POWER SUPPLY TO TEMPORARY SITE FACILITIES ALMOST COMPLETED
CONTINUOUS
DELIVERY OF STEEL REBAR