23 February, 2015

23.02.15



 STS PREPARING FOR AXIAL TENSILE LOAD TEST ON TP02

 LAST REACTION PILES 20/1 CONCRETED ON 21/02/2015

 PILE HEAD DEMOLISHING AND REINFORCEMENT PLACING FOR OTHER PILE CAPS ONGOING

  CONCRETING OF PILE CAPS IN PROGRESS

  CURING OF ALREADY POURED PILE CAPS ONGOING

HYDRAULIC JACKS FOR TESTING

 
ARRIVAL OF NWRT’S MOBILE CRANE 120 T CAPACITY 

 FENCING OF WEST, NORTH AND EAST SIDE COMPLETED AND AT SOUTH SIDE IN PROGRESS

 POLES INSTALLATION FOR POWER SUPPLY TO TEMPORARY SITE FACILITIES ALMOST COMPLETED

CONTINUOUS DELIVERY OF STEEL REBAR