24 February, 2015

24.02.15

   SAFETY INDUCTION EVERY TUESDAY MORNING, FOR REMINDING ZERO TOLERANCE POLICY & SAFETY FIRST.
 STS IS READY FOR AXIAL TENSILE LOAD TEST ON TP02 

LOADS FOR MAINTAIN LOAD TEST ON TP01 READY

 DEMOLISHING OF PILE HEADS IN PROGRESS

 PREPARATION OF REINFORCEMENT FOR PILE CAPS ON GOING

 STRIKING OF  FORMWORK 

 CURING OF PILE CAPS REGULARLY 

 SURVEYOR TEAM AT EAST SIDE FOR SETTING OUT OF MC’S TEST PILES

 PILING WORK FOR MC’S TEST PILES AT SOUTH-EAST IN PROGRESS

NWRT’S MOBILE CRANE 120 TON CAPACITY IS ALMOST OPERATIONAL