24 August, 2016

24.08.16

Boiler view from Air preheater back end
 Boiler Pressure Part-upper backpass rear & left wall panels 
 Boiler Pressure Part-upper backpass rear & left wall panels
 B63 STH View to North East - OH Crane moved to next bay to allow access to STG table top
B63 STH/B63STG  View to North, repaired STG column reaching table top level
B63 STH View to South - Steel Structure in progress
B63 STH North side substructure activities resumed
B63 STH North side substructure activities resumed
B30 CEB View to South 
B35 BEB Electrical network backfilling in progress
B35 BEB Electrical network interface
B07 ESP South CTO in progress
B07 ESP Foundation and Depac North side
L04 FGD pump building rebar in progress
L07 WFGD Service building pile head preparation & rebar in progress
WFGD Absorber embedded ring installation in progress
WFGD Ductworks ground assembly
B10 ID Fans foundation activities started
 B68 GSUT foundation getting ready for rebar
 B68 UAT Foundation pedestal & containment walls in progress
F05 SST Switchyard excavated 
 Drainage works South of HV Switchyard
D08 Ash sub-distribution bldg rebar in progress
E07 Electrical Building for CW
E04 Cooling Tower View to East