Plant view from South-West side
B63 - STH view from South-East side
B63 - STH West side wall cladding erection activities
B63 - STH view from North-East side
B63 - STH West side staircase structure erection activities
B63 - STH West side staircase erection activities
B63 - STH North side civil work activities
G28 - Oil & Firefighting Water Recovery Pit electrical equipment installation
G28 - Oil & Firefighting Water Recovery Pit pipe erection activities
B64 - STH loading bay area steam blow pipe erection activities
B64 - STH loading bay area steam blow pipe erection activities
B63 - STH area Elev. +14.00 m view from East side
B64 - ST turbine area steam blow pipe erection activities
B64 - ST turbine area steam blow pipe erection activities
B64 - ST turbine view from North-West side
B64 - ST turbine valve insulation installation
B64 - ST turbine valve insulation installation
B64 - ST turbine valve insulation installation
B64 - ST turbine valve insulation installation
B64 - ST turbine crossover pipe insulation installation
B64 - Generator South-East area steam blow pipe erection activities
B64 - Generator South-East area steam blow pipe erection activities
B64 - STH BFWP 1 area view
B64 - STH BFWP 2 area view
B63 - STH HP BIS Heaters insulation installation
B64 - STH Feedwater Tank insulation installation
B63 - STH pipe erection activities
B63 - STH HP Heaters area view
B63 - STH HVAC at Elev. +14.00 m level erection activities
B63 - STH Excitation transformer area view
B95 - Condensate Polishing Plant area view from South-East side
Steam Blow Silencer equipment installation
B01 - Boiler area view from South-East side
B01 - Boiler South FD & PA Fans area view
B01 - Boiler North FD & PA Fans area view
B06 - Boiler Coal Bunker Station view from South side
B30 - CEB Electrical Bldg. area view from South-West side
B30 - CEB Electrical Bldg. main control room view
B30 - CEB Electrical Bldg. programming room view
B30 - CEB Electrical Bldg. meeting room view
B30 - CEB Electrical Bldg. server room view
B68 - Transformer area view from North side
F05 - HV 230 kV Switchyard area view from B30 - CEB Electrical Bldg.
B07 - ESP area view from South-East side
B07 - ESP view from South-West side
B07 - ESP 1 view from North-East side
B07 - ESP 2 view from South side
B17 - Flue Gas Ducts connection to B07 - ESP 1 view from North-West side
B17 - Flue Gas Ducts towards B10 - Boiler ID Fan B ducts insulation installation
WFGD area view from South-East side
WFGD area view from North side
WFGD area view from East side
WFGD area view from South-West side
L04 - WFGD Pump Bldg. wall cladding installation
L04 - WFGD Pump Bldg. wall cladding installation
L04 - WFGD Pump Bldg. and L38 - Local Gypsum Slurry Tank area view from South-East side
L05 - WFGD Absorber / Reactor Tower and L38 - Local Gypsum Slurry Tank area view from North-East side
L05 - WFGD Absorber / Reactor Tower elevator area structure view
L05 - WFGD Absorber / Reactor Tower area cable pulling activities
L06 - WFGD Electrical Bldg. view from South-West side
L06 - WFGD Electrical Bldg. view from North-West side
L06 - WFGD Electrical Bldg. electrical cable pulling activities
L06 - WFGD Electrical Bldg. electrical cable pulling activities
L06 - WFGD Electrical Bldg. electrical cable & tray view
L06 - WFGD Electrical Bldg. electrical cable termination activities
L06 - WFGD Electrical Bldg. electrical panel view
L06 - WFGD Electrical Bldg. electrical panel testing activities
L06 - WFGD Electrical Bldg. electrical cable termination activities
L06 - WFGD Electrical Bldg. electrical panel view
L06 - WFGD Electrical Bldg. electrical cable termination activities
L06 - WFGD Electrical Bldg. electrical battery room view
L06 - WFGD Electrical Bldg. electrical marshalling panel cable termination activities
L06 - WFGD Electrical Bldg. electrical marshalling panel cable termination activities
L07 - WFGD Service Bldg. gypsum storage foundation area
L09 - WFGD Auxiliary Storage Tank area view from East side
L09 - WFGD Auxiliary Storage Tank area view from South-West side
L24 - WFGD Ducts view from South-East side
L24 - WFGD Ducts area drainage civil work activities
L36 - WFGD SRS. Bldg. and Service Bldg. area view from South-East side
C01 - Fuel Oil Storage Tank view from B30 - CEB Electrical Bldg.
C01 - Fuel Oil Storage Tank fueling activities
C01 - Fuel Oil Storage area view from North-East side
G10 - Emergency Diesel Generator area view from B30 - CEB Electrical Bldg.
C03 - Fuel Oil Pumping Station pump equipment view
Auxiliary Steam piperack crossing pipe insulation installation
Auxiliary Steam piperack crossing pipe insulation installation
Auxiliary Steam pipe insulation installation
G11 - Boiler Firefighting Pump House area view from West side
G11 - Boiler Firefighting Pump House pipe sleepers installation
G32 - Neutralization Basin and G28 - Oil & Firefighting Water Recovery Pit area civil work activities
G60 - Chemical Bulk Storage Bldg. area civil work activities
B94 - Air Preheaters Washing Basin area view from East side
D01 - Fly Ash Silo Storage Tank erection activities
D01 - Fly Ash Silo Storage Tank erection activities
D06 - Ash Transfer Tower and D07 - Ash Slag Conveyors structure erection activities
D06 - Ash Transfer Tower structure erection activities
D23 - Ash Receiving Station view from South-East side
D30 - Ash Loading Station view from North-East side
D08 - Fly Ash Sub-Distribution Bldg. view from South-West side
D08 - Fly Ash Sub-Distribution Bldg. view from South-East side
C08 - Lignite Sub-Distribution Bldg. view from South-West side
H03 - Piperack towards B07 - ESP area view from North-East side
L15 - Gypsum Transfer Tower and L12 - Gypsum Conveyors structure erection activities
K4 - Guard House civil work activities
Plant South side of Transformer area road work activities
Plant South-West side of Switchyard area road work activities
Plant East side of Guard House area road work activities
Plant South side of STH area road work activities
Plant South side of STH area road work activities
Plant South side of STH area road work activities
Plant South side of Boiler area road work activities
Plant South side of ESP area road work activities
Plant South side of ESP area road work activities
Plant South side of ESP area road work activities
Plant South side of WFGD area road work activities
Plant South side of WFGD area road work activities
Plant South side of Cooling Tower area road work activities
Plant East side of WFGD area drainage work activities
Plant East side of WFGD area road & drainage work activities
Plant West side of Cooling Tower Electrical Bldg. area drainage work activities
Plant West side of Cooling Tower area drainage work activities