09 March, 2018

09-03-18

Plant view from North-West side
Plant view from South-West side
B63 - STH West side staircase structure erection activities
B63 - STH North side civil work activities
B01 - Boiler North FD & PA Fans area view
B01 - Boiler North ID Fan A view
B07 - ESP 1 view from North-East side
B07 - ESP 1 view from L05 - WFGD Absorber / Reactor Tower
B07 - ESP 1 penthouse view from L05 - WFGD Absorber / Reactor Tower
B07 - ESP 2 view from L05 - WFGD Absorber / Reactor Tower
B17 - Flue Gas Ducts connection to B07 - ESP 1 view from North-West side
WFGD area view from South-East side
WFGD area view from North side
WFGD area view from L07 - WFGD Service Bldg. East side
WFGD area view from South-West side
L04 - WFGD Pump Bldg. and L38 - Local Gypsum Slurry Tank area view from South-East side
L04 - WFGD Pump Bldg. view from West side
L05 - WFGD Absorber / Reactor Tower Emergency Quench Tank area view
L05 - WFGD Absorber / Reactor Tower Primary Hydrocyclone area view
L05 - WFGD Absorber / Reactor Tower wall insulation & cladding erection activities
L05 - WFGD Absorber / Reactor Tower area tank erection activities
L06 - WFGD Electrical Bldg. view from L05 - Absorber / Reactor Tower
L06 - WFGD Electrical Bldg. area view from L05 - Absorber / Reactor Tower
L06 - WFGD Electrical Bldg. electrical cable pulling activities
L06 - WFGD Electrical Bldg. electrical panel view
L06 - WFGD Electrical Bldg. electrical battery room view
L06 - WFGD Electrical Bldg. electrical panel & cable area view
L06 - WFGD Electrical Bldg. electrical panel view
L06 - WFGD Electrical Bldg. electrical marshalling panel cable termination activities
L07 - WFGD Service Bldg. view from L05 - Absorber / Reactor Tower
L07 - WFGD Service Bldg. and H03 - Piperack view from North side
L07 - WFGD Service Bldg. Gypsum discharge conveyor view
L07 - WFGD Service Bldg. vacuum belt filter conveyor view
L07 - WFGD Service Bldg. Gypsum discharge conveyor view
L09 - WFGD Auxiliary Storage Tank lamination installation
L10 - WFGD Booster Fans area cable pulling activities
L24 - WFGD Ducts insulation & cladding erection activities
L24 - WFGD Ducts insulation & cladding erection activities
L24 - WFGD Ducts area GGH sealing gas fan & pipe erection activities
L24 - WFGD Ducts insulation installation
L24 - WFGD Ducts painting activities
L36 - WFGD SRS. Bldg. and Service Bldg. area view from South-East side
L36 - WFGD SRS. Bldg. cable termination activities
L36 - WFGD SRS. Bldg. pumps installation
C01 - Fuel Oil Storage area view from North-East side
G08 - Compressed Air Production Bldg. area view from North-West side
Auxiliary Steam piperack crossing pipe insulation installation
Auxiliary Steam piperack crossing pipe insulation & cladding installation
G11 - Boiler Firefighting Pump House pipe sleepers installation
G11 - Boiler Firefighting Pump House pipe erection activities
G32 - Neutralization Basin area civil work activities
B94 - Air Preheaters Washing Basin area civil work activities
B94 - Air Preheaters Washing Basin view from L05 - WFGD Absorber / Reactor Tower
D01 - Fly Ash Silo Storage Tank erection activities
D06 - Ash Transfer Tower structure erection activities
D01 - Fly Ash Silo Storage Tank and Ash Loading & Receiving station area view from L05 - Absorber Tower
D23 - Ash Receiving Station view from L05 - WFGD Absorber / Reactor Tower
C08 - Lignite Sub-Distribution Bldg. area view from South-West side
C08 - Lignite Sub-Distribution Bldg. area view from South-East side
C08 - Lignite Sub-Distribution Bldg. electrical panel view
C08 - Lignite Sub-Distribution Bldg. electrical panel testing activities
C06 - Coal Conveyors view from L05 - WFGD Absorber / Reactor Tower
C06 - Coal Conveyors and H03 - Piperack view from South-East side
C07 - Transfer Tower #4 equipment installation
L15 - Gypsum Transfer Tower view from East side
L15 - Gypsum Transfer Tower view from L05 - WFGD Absorber / Reactor Tower
L15 - Gypsum Transfer Tower discharge conveyors towards L07 - WFGD Service Bldg. erection activities
H03 - Piperack towards B07 - ESP 1 area civil work activities
E07 - Cooling Tower Electrical Bldg. view from South-West side
G42 - Fire Fighting Pumping Station view from South-East side
Acid cleaning temporary collecting pond area view
K4 - Guard House civil work activities
Plant South side of Transformer area road work activities
Plant South side of Switchyard area road work activities
Plant South side of WFGD area road work activities
Plant South side of Cooling Tower area road work activities
Plant East side of WFGD area road work activities
Plant South side of Cooling Tower area drainage work activities
Plant East side of WFGD area drainage work activities
Plant East side of WFGD area drainage work activities
Plant East side of WFGD area road & drainage work activities
Plant South side of ESP area drainage civil work activities
Plant South side of ESP ducts area underground cable duct civil work activities
Plant South side of ESP ducts area underground cable conduit pipe installation
Plant South side of ESP ducts area underground cable conduit pipe installation
Plant North side of ESP area underground civil work activities
Plant North side of ESP area underground fire fighting pipe installation
Plant North side of ESP area underground fire fighting pipe installation