05 April, 2016

05.04.16


Boiler View to South East
Mills Bay Tier 4
AirPreheater ready for lifting
PA Fan Foundation South
Electrical Network to PA/FD fan South
Furnace cavity, Tier 4 Columns started
Windbox connecting duct section 1 erection in progress
PA/FD Fan Foundations North
Tier 4 commenced over hanging steel backpass north
Boiler Airpreheater view to south
Boiler overall view from North East
Boiler Pulverizer view from North
Boiler Pulverizers View from South
Boiler Mills Bay view from South West
B63 STH View to North
B63 STH View to North West
B63 STH View to South
B64 SGT Foundation Pile head preparation
B64 STH Anchor Bolts installation
B30 CEB
Electrical Network to CEB
H03 Pipe Rack to CEB
H03 North of B35 BEB
B35 BEB pile head preparantion in progress
Electrical Network to BEB

 L09 Emergency scrubber dump foundation ready for pouring

 L09 Emergency scrubber dump foundation pouring ceremony
L35 process water tank foundation poured
L38 Local gypsum slurry tank foundation poured
 WFGD Area excavation and pile head preparation (H03/L24)
B07 - ESP foundations excavation and blinding
B07 - ESP foundations excavation and blinding

C01 Fuel Oil Tank Foundation
CW pipe 3rd trust block north of ESP started
CW Pipes view to west
CW Pipes Cofferdam to Pump Station view to North
Electrical network from E07 to E06/E12
E04 Cooling Tower view to East
B02 Chimney 