05 February, 2018

05-02-18

Plant view from South-West side
Plant view from North-West side
B63 - STH North side wall cladding erection activities
B63 - STH view from South-East side
B63 - STH West side wall cladding erection activities
B01 - Boiler South FD Fans & PA Fans area view
B01 - Boiler Submerged Scrapper Conveyor towards D07 - Slag Conveyor module structure erection activities
B01 - Boiler Submerged Scrapper Conveyor towards D07 - Slag Conveyor roller installation
B01 - Boiler Sump Pit area pipe erection activities
B02 - Stack CEMS equipment installation
B06 - Boiler Coal Bunker Station view from North side
B06 - Boiler Coal Bunker Station view from South side
B68 - Transformer area firefighting deluge system hydro-test activities
B07 - ESP area view from South-East side
B07 - ESP view from South-West side
B07 - ESP 1 ducts insulation & cladding installation
B07 - ESP 2 ducts insulation & cladding installation
B17 - Flue Gas Ducts towards B07 - ESP 1 ducts erection activities
B17 - Flue Gas Ducts crossover dampers insulation & cladding installation
WFGD view from South-East side
WFGD view from North side
L04 - WFGD Pump Bldg. wall cladding installation
L04 - WFGD Pump Bldg. wall cladding installation
L04 - WFGD Pump Bldg. wall cladding installation
L04 - WFGD Pump Bldg. wall cladding installation
L06 - WFGD Electrical Bldg. staircase erection activities
L06 - WFGD Electrical Bldg. view from North-West side
L05 - WFGD Absorber / Reactor Tower and L38 - Local Gypsum Slurry Tank view from East side
L24 - WFGD Ducts view from South-East side
L24 - WFGD Ducts area view from South-West side
C01 - Fuel Oil Storage Tank area view from West side
C01 - Fuel Oil Storage Tank painting work activities
C03 - Fuel Oil Pump Station and C01 - Fuel Oil Storage Tank view from North-East side
G08 - Compressed Air Production Bldg. area view from North-West side
Auxiliary Steam piperack crossing pipe erection activities
Auxiliary Steam piperack crossing pipe erection activities
G32 - Neutralization Basin civil work activities
B94 - Air Pre-Heater Washing Basin civil work activities
G11 - Boiler Firefighting Pump House civil work activities
D01 - Fly Ash Silo Storage Tank erection activities
D06 - Ash Transfer Tower structure erection activities
D06 - Ash Transfer Tower Conveyors module erection activities
D07 - Slag Conveyors module and G11 - Boiler Fire Fighting Pumping House area view
D23 - Ash Receiving Station view from South-West side
D23 - Ash Receiving Station view from South-East side
D23 - Ash Receiving Station view from South-East side
D23 - Ash Receiving Station bridge connection towards D30 - Ash Loading Station view from East side
TP - M09 : Fuel Oil System tie-in point at EGAT existing plant pipe erection activities
TP - M09 : Fuel Oil System tie-in point towards D23 - Ash Receiving Station pipe erection activities
D30 - Ash Loading Station view from North-East side
D30 - Ash Loading Station view from North-East side
D08 - Fly Ash Sub-Distribution Bldg. view from North-West side
D08 - Fly Ash Sub-Distribution Bldg. view from South-West side
D08 - Fly Ash Sub-Distribution Bldg. view from South-East side
D20 - Fly Ash Compressor Bldg. view from West side
D20 - Fly Ash Compressor Bldg. view from North side
C08 - Lignite Sub-Distribution Bldg. area view from South-West side
C08 - Lignite Sub-Distribution Bldg. area view from North-East side
C06 - Coal Conveyors module structure view from North-East side
H03 - Piperack towards B07 - ESP view from East side
L12 - Gypsum Conveyors view from East side
L15 - Gypsum Transfer Tower structure erection
L15 - Gypsum Transfer Tower view from East side
L15 - Gypsum Transfer Tower structure erection
G42 - Fire Fighting Pumping Station & C07 - Transfer Tower #3 area view from South-East side
G42 - Fire Fighting Pumping Station & H03 - Piperack area view from South-West side
E04 - Cooling Tower view from North-East side
G05 - Demineralized Water Bldg. view from South-East side
G05 - Demineralized Water Bldg. view from South-West side
G07 - Demineralized Water Storage tank area view from North-East side
G02 - Service Water Tank view from North side
G02 - Service Water Tank hydro-test activities
G05 - Demineralized Water Pump shelter erection activities
G02a - Demin Filtrate Water Tank view from South side
G05 - Demineralized Water Bldg. internal view
G05 - Demineralized Water Bldg. internal view
K04 - Guard House civil work activities
Acid Cleaning process
Acid Cleaning process
Plant South-West side of Switchyard area road work activities
Plant North-West side of Switchyard area road work activities
Plant South side of Transformer area road work activities
Plant South side of Boiler Bunker area road work activities
Plant South side of Boiler area road work activities
Plant South side of WFGD area road work activities
Plant South side of Transformer area drainage civil work activities
Plant South side of ESP area drainage civil work activities
ESP West side area drainage civil work activities
Plant South side of WFGD area underground fire fighting pipe installation activities
Plant East side of WFGD area underground fire fighting pipe installation activities
Plant East side of WFGD area underground drain pipe installation activities