26 February, 2018

26-02-18

Plant view from West side
B63 - STH view from North-East side
B63 - STH West side staircase structure erection activities
B63 - STH area Elev. +14.00 m view from West side
B64 - ST turbine view from North side
B64 - ST turbine view from North-West side
B64 - ST turbine area steam blow pipe erection activities
B64 - Generator South-West area steam blow pipe erection activities
B64 - Generator South-East area steam blow pipe erection activities
B64 - STH BFWP 1 view
B64 - STH BFWP 2 view
B64 - STH Feedwater Tank insulation installation
B63 - STH HP BIS Heaters insulation installation
B63 - STH electrical cable trays erection activities
B63 - STH HVAC ducts erection activities
B63 - STH Firefighting pipe & equipment installation
B30 - CEB Electrical Bldg. Meeting room balcony area view
B68 - Transformer view from South-West side
B68 - Transformer area view from South side
B68 - Transformer area view from B30 - CEB Electrical Bldg.
B68 - Transformer Energization activities 
F05 - 230 kV HV Switchyard area view from B30 - CEB Electrical Bldg.
C01 - Fuel Oil Storage Tank view from B30 - CEB Electrical Bldg.
G10 - Emergency Diesel Generator area view from B30 - CEB Electrical Bldg.
G08 - Compressed Air Production Bldg. area view from North-West side
Auxiliary Steam piperack crossing pipe insulation erection activities
Auxiliary Steam piperack crossing pipe erection activities
D01 - Fly Ash Silo Storage Tank and D06 - Ash Transfer Tower structure erection activities
D06 - Ash Transfer Tower structure erection activities
D07 - Slag Conveyors module erection activities
G11 - Boiler Firefighting Pump House area view from West side
Plant South side of STH area road work activities
Plant North side of Switchyard area road work activities
Plant West side of Switchyard area road work activities
Plant South-West side of Switchyard area road work activities