30 December, 2017

30-12-17

B64 - ST turbine view from North side
B63 - STH FW area Elev. +14.00 m view from East side
B63 - STH area Elev. +14.00 m view from West side
B63 - STH CPP pipe area view from Elev. +14.00 m
B63 - STH Loading Bay area view from Elev. +14.00 m
B64 - BFWP view from Top (Elev. +14.00 m)
B64 - ST turbine view from North-West side
B64 - ST turbine view from North-East side
B64 - Generator area view from South-East side
B64 - Generator view from South-West side
B64 - Generator view from South-East side
B64 - Generator protection cabinet cable termination activities
B64 - STH BFWP enclosure structure erection activities
B63 - STH HP BIS Heater insulation activities
B63 - STH HP Heaters insulation activities
B63 - STH HP Heaters insulation support erection activities
B63 - STH HP Heaters insulation cladding erection activities
B63 - STH WSC pipe insulation activities
B01 - Boiler Seal Air Booster Fan foundation civil work activities
B01 - Boiler Submerged Scrapper Conveyor Sluice Pump Skid installation activities
B01 - Boiler Slag Conveyor support structure erection activities
B01 - Boiler Slag Conveyor platform erection activities
B01 - Boiler Pyrite Hopper Header pipe erection activities
B01 - Boiler furnace insulation erection activities
B06 - Boiler Coal Bunker feeder equipment view
B06 - Boiler Coal Bunker Tripper Deck rail erection activities
B06 - Boiler Coal Bunker Tripper Deck rail erection activities
B06 - Boiler Coal Bunker Tripper Deck rail from C06 - Coal Conveyors support erection activities
B07 - ESP and B17 - Flue Gas Ducts view from B01 - Boiler
B17 - Flue Gas Ducts towards B07 - ESP 1 ducts erection activities
B17 - Flue Gas Ducts towards B07 - ESP 2 ducts erection activities
WFGD North-West side view from B01 - Boiler
WFGD South-West side view from B01 - Boiler
L05 - WFGD Absorber / Reactor Tower view from B01 - Boiler
G11 - Boiler Fire Fighting Pumping House civil work activities
D01 - Fly Ash Silo Storage Tank erection activities
D06 - Ash Transfer Tower structure erection activities
D07 - Slag Conveyor module pre-assembly and H03 - Piperack view from B63 - STH
D23 - Ash Receiving Station and D30 - Ash Loading Station structure erection activities
G32 - Neutralization Basin and G28 - Oil & Fire Fighting Water Recovery Pit view from B01 - Boiler
G60 - Chemical Bulk Storage and G32 - Neutralization Basin area view from B01 - Boiler
H03 - Piperack towards B07 - ESP view from B01 - Boiler
C06 - Coal Conveyors and H03 - Piperack view from B01 - Boiler
C06 - Coal Conveyors and L12 - Gypsum Conveyors view from B01 - Boiler
C07 -Transfer Tower #4 view from B01 - Boiler
L12 - Gypsum Conveyors module erection activities
Acid Cleaning temporary collecting pond area view