B63 - STH view from South-East side
B01 - Boiler plant view from South-East side
B06 - Boiler Coal Bunker Station view from South side
B01 - Boiler cable pulling activities
B01 - Boiler pipe insulation installation activities
B01 - Boiler wall insulation installation
B07 - ESP and L24 - WFGD Ducts area view from South-East side
B07 - ESP area view from South-West side
B07 - ESP 2 view from South side
B07 - ESP pipe erection activities
B10 - ID Fans lube oil flushing activities
B10 - ID Fans lube oil flushing activities
B10 - ID Fans cable termination activities 
B17 - Flue Gas Ducts erection activities
B94 - Air Pre-Heater Washing Basin area civil work activities
L24 - WFGD Ducts area view from South-East side
G28 - Oil & F.F Recovery Pit at West B63 - STH civil work activities
F05 - 230 kV HV Switchyard area drain trench civil work activities
H03 - Piperack and C06 - Coal Conveyors view from South-East side
C06 - Coal Conveyors & C07 - Transfer Tower #3 structure erection activities
C06 - Coal Conveyors structure erection activities
C06 - Coal Conveyors module structure pre-assembly activities
C06 - Coal Conveyors module structure pre-assembly activities
C06 - Coal Conveyors module structure pre-assembly activities
Plant South side of WFGD area underground drain pipe installation activities
Plant South side of Boiler area underground drain pipe installation activities