07 December, 2017

07-12-17

Plant view from West side
Plant view from North-West side
B63 - STH West side area civil work activities
B63 - STH West side area civil work activities
B63 - STH West side civil work activities
B63 - STH Transformer Excitation equipment installation activities 
B01 - Boiler Slag Conveyor foundation civil work activities
B01 - Boiler North FD Fan and PA Fan lube oil flushing activities
B17 - Flue Gas Duct to ESP 1 erection activities
B30 - CEB Electrical Bldg. area view from South-West
B30 - CEB Electrical Bldg. and F05 - Switchyard area road work activities 
B30 - CEB Electrical Bldg. Programming room view
B30 - CEB Electrical Bldg. Main Control room view
B30 - CEB Electrical Bldg. commissioning activities
B35 - BEB Electrical Bldg. cable termination activities
B35 - BEB Electrical Bldg. cable termination activities
B35 - BEB Electrical Bldg. electrical panels view
F05 - 230 kV HV Switchyard area view from B30 - CEB Electrical Bldg.
B94 - Air Pre-Heater Washing Basin area civil work activities
G28 - Oil & Fire Fighting Water Recovery Pit area civil work activities 
G60 - Chemical Bulk Storage Bldg. and G32 - Neutralization Basin area civil work activities
L04 - WFGD Pump Bldg. view from North-East side
L24 - WFGD Duct area underground cable duct civil work activities
G10 - Emergency Diesel Generator area view from B30 - CEB Electrical Bldg.
 C01 - Fuel Oil Storage Tank area view from West side
C01 - Fuel Oil Storage Tank area view from B30 - CEB Electrical Bldg.
Auxiliary Steam piperack crossing from existing EGAT plant view
Auxiliary Steam pipe on piperack erection activities
Auxiliary Steam pipe erection activities
G11 - Boiler Fire Fighting Pumping House civil work activities 
D01 - Fly Ash Silo Storage Tank area view from North-East side
D23 - Ash Receiving Station structure erection activities
D30 - Ash Loading Station structure erection activities
C06 - Coal Conveyors module structure pre-assembly activities
C06 - Coal Conveyors module structure pre-assembly activities
C06 - Coal Conveyors module structure pre-assembly activities
C06 - Coal Conveyors structure erection activities
C06 - Coal Conveyors gallery module #1 erection activities
H03 - Piperack towards B07 - ESP pipe & cable trays erection activities
H03 - Piperack towards B07 - ESP pipe erection activities
Plant South side of WFGD area underground drain pipe installation activities
Plant South side of Boiler area underground drain pipe installation activities