Boiler general View from Laydown, getting ready to erect 1st Tier#6 columns later today
Boiler Air Preheater side
Boiler: Duct Erection earlier is easier
Boiler Mills Bay
Turbine Hall pile cap rebar & Table pile cap foundation at the back
ESP: pile cutting
CEB pile caps
CEB (B30): 3 pile Caps poured on 03rd may, under curing
BEB (B35) area
Site general View from East (cooling Tower 1st)
Boiler steel and pressure part laydown/prefabrication area overview
Turbine Hall steel structure fire proofing on going
Turbine Hall steel structure fire proofing on going
Turbine Hall steel structure fire proofing on going
Delievery of Turbine Table embedments