Boiler Girder F (101 T) unloading in cavity by 4 cranes: main: 250T & 180T, tailing 2*70T
Boiler Girder E (101T) South of Boiler on trailer during EHS management walkdown
Boiler Girder D (44T) in TJEL laydown south of Boiler
Boiler girder F tilted & travelling to final position in back pass with 2 main cranes
Boiler Girder F in final position, back pass area
Boiler Girder F in final position, back pass area
Boiler Girder F in final position, back pass area
Boiler Mills Bay, secondary steel, staircase & grating
Turbine Hall, Table fondation nearing casting (1 500 m3)
Turbine Hall, next Pile cap reinforcement on going