05 May, 2016

05.05.16 Boiler girders delivery

All 6 Boiler girders delivered early this morning
 6 boiler boiler girders parked just outside site
 Boiler girder on trailer
 Arrived from 06h00 am to 08h00 am this morning
 Transport of 1st girders this evening to site after site is clear of traffic 
 Boiler view from Mills Bay side
 Boiler view from Air Preheater side
 Boiler: Tier # 6 erections started yesterday
 Re-preparation of road for girder delivery to boiler cavity
 Boiler South View: access road for girders
Central Electrical Building: Pile caps progressing