Boiler Mills Bay view from West
Boiler View to South West - Air Heater Structure
Boiler View to North West - 600T crane boom down for reconfiguration
Header lifted into temporary frame, preparation and fit-up in progress
Coal Silo Barrels & Ducts ground assembly
Windbox Connecting Duct Sect. 1 & Primary Air Duct view to North
Windbox Connecting Duct Sect. 1 View to South
Boiler Tier #6 Erection in progress
Boiler Main Girders View inside cavity to East
Boiler Main Girders View inside cavity to East
Coal Feeder decking in progress
Boiler Main Girders View inside cavity to South
Pressure part R04 LTRH Coils assembly fit up in progress
S39-S40 placed on fabrication beds
Terminals tubes fit up to R08 LTRH Header
Boiler view to South West
PA Fan foundation South, electrical network in progress
PA Fan foundation North, electrical network in progress
FD Fan foundations North
B64 STG foundation poured on 7th May (1400m3).
B63 STH View to North East - Pile Cap A3 rebar progress
B63 STH View to North West
Electrical Network south of B30
B30 View to South East
B30 View to North East
B30 View to South
B35 BEB
ESP Tower Crane assembly in progress
ECS : WFGD Area view to North
ECS : WFGD L24 Area view to North
ECS : WFGD Area view to North
B07 ESP foundations area view to South
H03 Pipe Rack North of Boiler
D30 Ash loading station
Electricla Network to D08
C01 FO Tank Foundation
CW pipes View to West
CW pipes View to East
CW pipes View to West
CW Pipes foundations to Pump Station in Progress
CW Pipes foundations to Pump Station in Progress
Cofferdam for CW pipe return line view to south
E04 Cooling Tower view to East
Underground Storage tanks excavation in progress (L60/E10/G40)