Turbine Hall West side pedestals
Turbine Hall East side: Turbine table pile cutting and preparation for pile cap/CEX shaft
Boiler, 600 T crane in operation since 02nd March afternoon
Boiler steel overview from air preheater side
Boiler PA/FD fan North backfilling
Boiler North East access to Boiler electrical building (B35) area
Fondations of FGD ducts between boiler & ESP
Boiler PA/FD Fan South fondations, backfilling
Boiler Mills: all 7 mills sole plates installed
Piling work, MC scope in ESP area
Main Cooling water trench, pipe laying
WFGD aux tank (emergency scrubber) lean concrete before pile cutting
Chimney stack: intstallation of winch for concreting bucket & delivery of Halimak, 3rd party inspection planned on 09th March
Chimney stack: intstallation of winch
Cooling tower civil bar bending shop after EHS improvment (EHS walk today)