 Turbine Hall West side pedestals
  Turbine Hall East side: Turbine table pile cutting and preparation for pile cap/CEX shaft
 Boiler, 600 T crane in operation since 02nd March afternoon
 Boiler steel overview from air preheater side
 Boiler PA/FD fan North backfilling
 Boiler North East access to Boiler electrical building (B35) area
 Fondations of FGD ducts between boiler & ESP
 Boiler PA/FD Fan South fondations, backfilling
 Boiler Mills: all 7 mills sole plates installed
 Piling work, MC scope in ESP area
 Main Cooling water trench, pipe laying
 WFGD aux tank (emergency scrubber) lean concrete before pile cutting
 Chimney stack: intstallation of winch for concreting bucket & delivery of Halimak, 3rd party inspection planned on 09th March
  Chimney stack: intstallation of winch 
Cooling tower civil bar bending shop after EHS improvment (EHS walk today)