25 March, 2016

25.03.16

 Boiler Air duct ground fabrication in Laydown area 1
 Boiler Mills Bay view from West 
Boiler Mills Bay view from South West
 Boiler View from North West
 Millside assembly erected onto foundation
 Boiler North side view
 Boile Airpreheater view to south
Boiler overall view from north east
Tier 3 Column installation
Hanging steel backpass view to north
Hanging steel furnace view to north
PA Fan Foundation South
Electrical networks FD Fan south
PA Fan Foundation North
Electrical networks FD Fan north
B63 STH View to north east
B64 STG foundation Excavation
B63 STH View to north west
 B63 STH View from North West
 B64 STG View to West pile head preparation
B63 STH - CW Pipes outlet welding

 B63 STH - CW Pipe outlet trust block 

 Electrical Network south of B30 CEB
 B30 CEB 
 Electrical Network north of B30 CEB
 Electrical Network north of B30 CEB
 H03 rack to CEB excavation 
 B35 CEB Excavation and pile head preparation  
 C01 Fuel Oil Tank pile head preparation
 CW Pipe cofferdam view to east
CW Pipes Cofferdam to Pump Station view to south

CW Pipes Cofferdam view to west
 B02 Chimney slipform in progress (1.8 meter on 12 hour shift) 
D08 fly ash intermediate silo


E04 Cooling Tower view to East 
Electrical network from E07 to E06/E12
 L09 Emergency scrubber dump foundation rebar in progress
H03 to WFGD excavation and pile head preparation
L38 Local gypsum slurry tank foundation rebar in progress
  L35 process water tank foundation ready for pouring
CW Pipes installation