08 March, 2016

07.03.16

 Turbine Hall East side from South (CW Outlet & CEX)
 Turbine Hall East side from North (CW outlet)
 CW pipes backfilled North of Turbine Hall - pipe rack pedestal
 Turbine Hall West side from North : CW inlet

 Turbien Hall North West corner: CW inlet & TH pedestals
 Central Electrical Building: excavation & pile cutting
 Boiler Mills Bay before Coal silo lift today
 Boiler: Hanging steel erection North side
 Boiler steel Overview from North East (air preheater on the left)
 Boiler steel North side: hanging steel
  Boiler steel North side: hanging steel
  Boiler secondary steel & staircase on the north side
 Boiler PA/FD Fans backfilling South side
 Boiler Mills sole plates
 Boiler Mills: underground conduits to Mills (lube oil)
 Boiler UG electrical pit to riser (south side)
 WFGD aux Tank L09, pile cutting
 Air cooling Tower pump station
 Cooling Water trench to Air cooling Towers
 CW pipes installation/welding (around WFGD area)
 CW pipes, concrete Trust blocks poured North of B35
 General View from area 7 laydowns
 Conveyors civil works in existing plant
 Conveyors civil works in existing plant
 Conveyors civil works in existing plant
Water tanks fondations in existing plant